Progress of the Pune Metro Rail project in the City twin city of Pimpri Chinchwad municipal Corporation is in full swings

NP NEWS NETWORk 

As in the Pimpri Chinchwad Municipal corporation (PCMC), Pune metro rail is one of the most ambitious projects undertaken to transform Pune city transport.

So far there is substantial progress made in PCMC reach and Deccan to Kothrud section.

[amazon_link asins=’B07D57FB43,9312147889,931214782X,B075F48D1S,9312147560,9312147897,B075F9HR4T,9312148559,B079VD4L4V’ template=’ProductCarousel’ store=’policenama100-21′ marketplace=’IN’ link_id=’a06db723-ba68-11e8-b37c-c5b37cb05cea’]

The work on R B M Road to Ramwadi and the underground has started recently and it will gain momentum soon.

In PCMC area, the highlight of the Pune metro rail project is executed with the state of the art project management tools such as Primavera, 5D BIM
Quality checks are inbuilt in the work execution system and highest attention paid to quality.

[amazon_link asins=’B0756J3186,B01FO6RIFO,B0771MGFK2,B06XVDC3X9,B07GKFQF47,B07CWPFW37,B07CWPHXH6,B07BLVY1F1′ template=’ProductCarousel’ store=’policenama100-21′ marketplace=’IN’ link_id=’ccd22846-ba68-11e8-aad8-8b46e142af40′]

Safety, Health, and Environment (SHE) are given the utmost priority and there is the dedicated team to monitor it.

All trees which need to relocate due to unavoidable circumstances were transplanted with modern technique in the same locality as far as possible.

Pune Metro is committed to reaching the Punekars through various initiatives such as Samwad, meetings, traffic awareness drives, Mahitee Kendra, and social media.

Recently Pune Metro has undertaken road safety awareness drive in an innovative manner, by deploying warden dressing up in Yam and Chitragupta outfits.

The Maheetee Kentra at Balgandharv Natyagruha has more than 400 visitors per day.

BJP Observers held meeting in Goa after Parrikar’s admission in AIIMS

The progress of Reach – 1 (PCMC)

Total 6 foundations completed in this month so far. Till date 198 foundations completed in this reach. Pilling completed in this month were 28 and total 435 in this reach so far. Eight piers were cast in this month and 160 in this reach so far. Four pillar cap completed in this month and 78 so far in this reach. Total 35 segments were cast in this month and total 865 so far in this reach. Five Girder was launched in this month and 30 so far in this reach.
Issues:

Pier 251 has been critically inspected by Mahametro quality team and experts from the industry. Attention is given to the pier as per the expert advice. Pune metro has audited the process and taken corrective action to avoid such incidences in future.
Pune metro is in consultation with military authorities for land at Khadki.