Extension of Metro project in Pune Municipal Corporation made a cut-put to BSNL

NP News Network

Pune

The Pune metro rail is one of the most ambitious projects undertaken to transform Pune city transport especially in the Pune Municipal Corporation (PMC) but it seems the work progress brings with a bit troublesome to local residences as during work it was alleged that some 3000 phones connection faced issued.

[amazon_link asins=’B001FWYGJS,B00JE6HMNY,9312141813,B00PVDF83A,B007O7J026,B00A0VCJPI,9351473279,9351449831,B077GPJ18B’ template=’ProductCarousel’ store=’policenama100-21′ marketplace=’IN’ link_id=’f0e52a05-ba6a-11e8-984e-efc6591a240c’]

So far there is substantial progress made in Pune’s twins city Pimpri Chinchwad area has reach and Deccan – Kothrud section.

The work on R B M Road to Ramwadi & underground has started recently and it will gain momentum soon.

[amazon_link asins=’B071SLC7Y9,9383157178,818778086X,B00UB0QK9Y,B072DXW6J4,B01HQ3P3LO,B00N23LDA8,9386348667,B012IDEGHE’ template=’ProductCarousel’ store=’policenama100-21′ marketplace=’IN’ link_id=’07be774d-ba6b-11e8-a35f-fd82e27b4bc8′]

The few highlights of the Pune metro rail project is executed with the state of the art project management tools such as Primavera, 5D BIM
Quality checks are inbuilt in the work execution system and highest attention paid to quality.
Safety, Health, and Environment (SHE) are given the utmost priority and there is the dedicated team to monitor it.

All trees which need to relocate due to unavoidable circumstances were transplanted with modern technique in the same locality as far as possible.

Pune Metro is committed and stressed to reach the Punekars through various initiatives such as Samwad, meetings, traffic awareness drives, mahitee kendra and social media.
Recently Pune Metro has undertaken road safety awareness drive in an innovative manner, by deploying warden dressing up in Yam and Chitragupta outfits.

The Maheetee kentra at Balgandharv Natyagruha has more than 400 visitors per day.

The progress of Reach – 2 From Vanaz to Ramwadi
Work on Pune Metro’s reach – 2 stretch from Vanaz to Ramwadi is progressing at fast pace.

BJP Observers held meeting in Goa after Parrikar’s admission in AIIMS

PCC is 129 number is completed out of 330 numbers, Pilling work is 165 out of 638, 7 numbers. Pile cap completed out of 105,112 footing work is completed out of 225.

The pier work at ground level section is 105 out of 330, upto pier cap work completed 44 number out of 330, pier cap portal beam completed 21 number out tthe otal of 273 pier cap,w ork of casting segment 311 out of 2576 same as 04 spans has been completed  out of 293 spans.

Explaining the Progress Details of River front Side it seem from the pier number 152 to 190 work river side area as below. There are around    26 number. PCC work is completed out of 59 numbers. 102 Pilling work is completed out of 204 Numbers. 25 number. Footing Pile cap work is completed out of 59 number.25 number pier work is completed upto gthe round level total of 59 number.

There are three numbers of pier completed upto pier cap button out of 59 number.
Apart from the highlight ,there are some issues like the Pune metro plan to held Samwad twice in wthe eek at R B Mill road to Ramwadi route to reach the residents.
Metro officials said, “All efforts has been made to minimise the traffic congestion in R B Mill road to Ramwadi reach by deploying traffic warden. BSNL cable was cut at Paud road Near More Vidyalaya while pilling work of pier no 323.

Pune metro communicate the notified area were pilling to be done to along with Pune Municipal Corporation (PMC), Maharashtra State Electricity Development Corporation Limited (MSEDCL), Bharat Sanchar Nigam Limited (BSNL) authorities before cthe ommencement of work.

The official said,” Further the Pune metro is taking utmost care by digging the notified area by manually upto two meter depth so that all utilities Sewer line, water pipeline, MSEDCL cables, telephone cables should not get damages. At the present instance ,the cable was found at the depth of 3 m. Pune metro is extending all necessary help to BSNL to restore the telephone lines.”